| S.No | TRAS Provider Name | DAM TRAS-Up Cleared (MWHr) (A) |
DAM TRAS-Up Energy Scheduled (MWHr) (B) |
DAM TRAS Up Energy Charges (Rs.) (C) |
DAM TRAS Up Commitment Charges (Rs.) (D) |
RTM TRAS-Up Cleared (MWHr) (E) |
RTM TRAS-Up Energy Scheduled (MWHr) (F) |
RTM TRAS Up Energy Charges (Rs.) (G) |
RTM TRAS Up Commitment Charges (Rs.) (H) |
Total Charges /compensation charge for TRAS Up (Rs) (I)= (C)+(D)+(G)+(H) |
DAM TRAS-Down Energy Scheduled (MWHr) (J) |
DAM TRAS-Down Charges to be paid back to pool (Rs) (K) |
RTM TRAS-Down Energy Scheduled (MWHr) (L) |
RTM TRAS-Down Charges to be paid back to pool (Rs) (M) |
Net Charges (N)=(I)-(K)-(M) |
(+) Payable from Pool to TRAS Provider/ (-) Receivable by Pool from TRAS Provider |
| 1 | Ramagundam Super Thermal Power Station (U1-6) NTPC Ltd. |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
| 2 | Ramagundam Super Thermal Power Station (U7) NTPC Ltd. |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | -29.19 | 9,979 | 9,979 | Receivable by Pool from TRAS Provider |
| 3 | NLC TPS-II Stage I NLC Ltd |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
| 4 | NLC TPS-II Stage II NLC Ltd |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
| 5 | NLC TPS-I Expansion NLC Ltd |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
| 6 | NLC TPS-II Expansion NLC Ltd |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
| 7 | Talcher Super Thermal Power Station Stage II NTPC Ltd. |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | -4128.19 | 3,39,203 | 3,39,203 | Receivable by Pool from TRAS Provider |
| 8 | Vallur Thermal Power Station NTECL Ltd. |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | -1284.29 | 1,70,951 | 1,70,951 | Receivable by Pool from TRAS Provider |
| 9 | NTPL NTPL Ltd. |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
| 10 | Simhadri Super Thermal Power Station Stage I NTPC Ltd. |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
| 11 | Simhadri Super Thermal Power Station Stage II NTPC Ltd. |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | -146.21 | 42,078 | 42,078 | Receivable by Pool from TRAS Provider |
| 12 | Kudgi Super Thermal Power Station Unit I NTPC Ltd. |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | -303.73 | 65,681 | 65,681 | Receivable by Pool from TRAS Provider |
| 13 | NNTPP NLC Ltd |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
| 14 | Telangana STPS NTPC Ltd. |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | -359.45 | 76,231 | 76,231 | Receivable by Pool from TRAS Provider |
| 15 | COASTAL |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | -1226.61 | 36,798 | -2000.87 | 60,026 | 96,824 | Receivable by Pool from TRAS Provider |
| 16 | SEILP2 |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | -1283.52 | 1,02,784 | -5431.71 | 17,17,811 | 18,20,595 | Receivable by Pool from TRAS Provider |
| 16 | SEILP1 |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | -826.28 | 2,34,663 | 2,34,663 | Receivable by Pool from TRAS Provider |
| 17 | APL Udupi(Karnataka-Intrastate) |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
| Total | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | -2510.13 | 1,39,582 | -14509.92 | 27,16,623 | 28,56,205 | Receivable by Pool from TRAS Provider |